WHY THIS CORRIDOR? WHY NOT AVOID OUR COMMUNITIES AND VALLEY?
Chalice Mining has selected a preferred infrastructure corridor through established rural residential communities in the heart of the Chittering Valley. But why was this route chosen, and why haven't residents been shown the evidence that alternatives avoiding their communities were properly considered?
For families who have built homes, raised children, established businesses, invested their savings and planned their futures here, this is not simply an engineering decision.
It is a decision with potentially enormous consequences for people's lives, properties, livelihoods, financial security and the natural environment they have chosen to live amongst.
Yet one fundamental question remains unanswered.
Could these impacts have been avoided in the first place?
ALTERNATIVE ROUTES — BUT ALTERNATIVES TO WHAT?
In its original 2024 Commonwealth environmental referral, Chalice identified two water-route options, two power-route options and additional contingencies.
Further investigations and environmental surveys followed during 2025.
By May 2026, Chalice had identified a preferred infrastructure corridor and was contacting landholders along that alignment.
Its subsequent environmental amendment proposed a single preferred corridor for the water pipeline and powerline.
But the alternatives publicly identified do not demonstrate that Chalice seriously evaluated a route avoiding the Chittering Valley's established rural residential communities altogether.
Instead, the published options concentrated on different alignments through the broader affected region.
Were routes bypassing these communities ever genuinely investigated?
If so, where are the maps, comparative assessments and reasons for rejecting them?
And if they were not investigated, why not?
Simply comparing several routes through the same affected communities does not answer the larger question of whether those communities could reasonably have been avoided altogether.
AVOIDING IMPACTS SHOULD COME FIRST
Western Australia's Environmental Protection Authority recognises a fundamental principle in environmental assessment: the mitigation hierarchy.
The first step is to avoid adverse environmental impacts wherever reasonably practicable.
Only then should attention turn to minimising, rehabilitating or offsetting impacts that cannot be avoided.
The EPA also recognises social surroundings as an environmental factor, including the social, cultural and aesthetic values of places important to communities.
So why shouldn't avoiding established homes, rural residential estates and environmentally sensitive areas be a priority when planning major mining infrastructure?
Chalice has discussed measures to reduce the impacts of its preferred corridor, including undergrounding the powerline through the rural residential zone near Maryville Heights.
But undergrounding a powerline does not remove the pipeline, excavation, construction disturbance, vegetation impacts or the ongoing presence of infrastructure.
Reducing the consequences of a chosen route is not the same as demonstrating that those consequences were unavoidable.
Before asking communities to accept decades of potential disruption and change, shouldn't the first question be whether there was a reasonable way to avoid imposing those impacts on them at all?
WHY WEREN'T COMMUNITIES MEANINGFULLY CONSULTED BEFORE THE ROUTE WAS CHOSEN?
This may be one of the most troubling aspects of the entire corridor-selection process.
Chalice says it undertook landholder engagement during 2025, including seeking access to properties for environmental surveys along potential routes.
Some landholders were contacted during those investigations.
But many residents along the subsequently preferred corridor did not learn that their properties and communities could be directly affected until May 2026.
By that stage, Chalice had already identified its preferred corridor through their rural residential estates.
Why weren't these communities meaningfully involved while the broader alternatives were still being investigated?
Requesting access for environmental surveys is not the same as consulting residents about the potentially life-changing consequences of selecting a particular route.
These are not empty parcels of land on an engineering map.
They are people's homes. Their retirement plans. Their livelihoods. Their children's futures. Properties purchased, developed and cared for over many years, often representing a lifetime of hard work.
Residents understand their local wildlife, waterways, fire risks, vegetation, seasonal conditions and the practical realities of living in these communities.
They also understand something that cannot be fully appreciated from an engineering drawing: what their homes and surroundings mean to them.
That knowledge, and the consequences of potentially losing the quiet enjoyment and security of their properties, should have informed the earliest comparison of alternative routes.
How can community impacts be adequately weighed if the people who would bear those impacts were not meaningfully involved while the options were being narrowed?
Consultation should not begin, for many affected residents, when the question has effectively changed from "Where should this infrastructure go?" to "How can we make this preferred route work?"
And being informed that a preferred corridor has been identified is not the same as being given a genuine opportunity to influence where that corridor should go.
The community should have been part of the decision-making process, not simply informed of its outcome.
WHAT WAS GIVEN THE GREATEST WEIGHT?
Chalice says its preferred corridor was identified using engineering data, environmental survey results and landholder feedback.
But identifying the information considered does not explain how competing priorities were weighed against one another.
Were construction costs and engineering convenience given greater weight than avoiding established communities?
Were alternatives that would have reduced impacts on homes and private properties rejected because they were more expensive?
How were impacts on mature woodland, wildlife habitat, waterways, farmland, bushfire risk and rural amenity compared between different routes?
Were the long-term consequences for affected families assessed before the preferred corridor was identified?
And how much importance was given to avoiding those impacts altogether?
We do not know.
It would be unfair to assume that construction costs determined the outcome without seeing the evidence.
But it is equally unreasonable to expect affected communities to accept that the preferred route represents the best overall outcome without being shown how that conclusion was reached.
A route that is cheaper or easier to construct is not automatically the route with the least overall impact.
And the full consequences of a decision cannot be measured by construction costs alone.
THE IMPACTS WON'T END WHEN CONSTRUCTION FINISHES
Chalice's proposed infrastructure includes a lengthy water pipeline, high-voltage electricity infrastructure and associated construction and maintenance requirements.
The preferred assessment corridor is approximately 100 metres wide. Chalice says this does not represent the final clearing footprint, which would be narrower.
But the physical footprint of infrastructure is only part of its potential impact.
There are also consequences for adjoining properties, vegetation, wildlife movement, waterways, access, amenity and the ongoing use and enjoyment of private land.
For some families, uncertainty has already affected how they view their future in the Valley.
These impacts deserve consideration from the earliest planning stages, not simply after an alignment has been selected.
The Gonneville Project has not yet received its required environmental approvals, and a final investment decision remains outstanding.
Yet residents are already facing the prospect of significant and potentially long-lasting changes to their homes and surroundings.
Why should communities be expected to accommodate these consequences without first being shown that reasonable alternatives to avoid them were properly examined?
ACCOUNTABILITY CANNOT WAIT
The time for meaningful transparency during the original route-selection process has already passed.
That opportunity was missed when communities were not meaningfully involved before Chalice identified its preferred corridor through their estates.
Residents should have been able to examine the alternatives, question the assessment criteria and raise the consequences for their homes and lives while those decisions were still being made.
Instead, many were informed only after Chalice had identified its preferred route.
That lost opportunity cannot be restored by releasing information months later, on Chalice's preferred timetable.
But the obligation to explain and justify the decision remains.
The full route comparisons, assessment criteria, rejected alternatives and reasons for their rejection should be publicly disclosed now, before further decisions affecting landholders and their properties are made.
Government authorities must also be prepared to independently scrutinise whether reasonable opportunities to avoid established communities were properly investigated.
Chalice cannot turn back the clock on meaningful early consultation. But it can be held accountable for the decisions made without it.
And accountability begins with showing the public the evidence.
We should not have to fight to discover why our communities were placed in the path of a corridor we were never given a meaningful opportunity to question before it was preferred.
WHERE IS THE TRANSPARENCY?
Chalice says its preferred corridor was selected following extensive investigations and consideration of engineering, environmental and community impacts.
Then show us the evidence.
Where are the alternative route maps? Where are the comparative assessments? Where is the explanation of why routes avoiding established rural residential communities were not preferred?
And where was the meaningful consultation with affected communities before that decision was made?
The opportunity for transparency during the original route-selection process has already been missed.
Many residents were not meaningfully consulted until after Chalice had identified its preferred corridor through their estates.
That lost opportunity cannot be restored by releasing information months later, at a time of Chalice's choosing.
But transparency and accountability are still required.
The full assessments and reasons for rejecting alternatives should be publicly available now, while the project remains subject to approvals and decisions affecting private land are still ahead.
Government authorities must also independently scrutinise whether reasonable opportunities to avoid these communities were properly investigated.
Transparency is not telling people what has already been decided. It is showing them the evidence, explaining the choices and being accountable for the consequences.
And if Chalice cannot demonstrate why these communities could not reasonably have been avoided, that raises an even more fundamental question.
On what basis was this corridor preferred in the first place?
SOURCES & OFFICIAL DOCUMENTS
Commonwealth EPBC Referral 2024/09839 — Gonneville Project
Original referral identifying alternative water and power infrastructure route options.
Chalice Gonneville — Infrastructure Update
Chalice's explanation of the 2025 investigations, landholder engagement and preferred infrastructure corridor.
https://www.gonnevilleproject.com.au/infrastructure-update/
Chalice Gonneville — Frequently Asked Questions
Information on preferred route selection, consultation, underground power and environmental amendments.
https://www.gonnevilleproject.com.au/faq/
WA EPA — Environmental Principles and Mitigation Hierarchy
https://www.epa.wa.gov.au/statement-environmental-principles-factors-and-objectives
WA EPA — Instructions for Preparing an Environmental Review Document
https://epa.wa.gov.au/forms-templates/instructions-how-prepare-environmental-review-document
Based on publicly available information as at 9 October 2026. The absence of a publicly demonstrated alternative avoiding established communities does not establish that no such option was considered internally.
The questions surrounding transparency do not end with the selection of the corridor. They also extend to the infrastructure decisions Chalice has attributed to community feedback.
Was underground power already under consideration?
There is another important question surrounding Chalice's decision to underground the proposed 132 kV powerline near Maryville Heights.
Chalice has presented the decision as a response to community feedback.
But infrastructure corridors, particularly high-voltage transmission lines, require substantial engineering investigations. Underground installation involves different technical requirements, construction methods, environmental considerations and costs from overhead transmission infrastructure.
Chalice had already been investigating infrastructure options and undertaking environmental surveys during 2025, before many residents along the preferred corridor were informed of its location in May 2026.
This raises an important question about the timing of the undergrounding decision.
Was underground power already being investigated as an engineering option before the community objections Chalice now credits with influencing its decision?
If so, what role did community feedback actually play in selecting that option?
And if the decision was made only after objections were received, what engineering investigations, environmental information and cost assessments supported it?
There is a significant difference between responding to community concerns and presenting an existing design option as a concession made because of those concerns.
The community deserves a transparent timeline showing when undergrounding was first considered, when it was assessed, when the decision was made and how community feedback influenced the outcome.
Without that information, the claim that undergrounding demonstrates meaningful community influence remains difficult to independently evaluate.
Source: Chalice Mining — Gonneville Project, Frequently Asked Questions (Infrastructure Corridor and Underground Power).
https://www.gonnevilleproject.com.au/faq/